Looks like this is going to be a great project - following
1968 Mini Van Restoration Project
Started by
owenlcr
, Jan 15 2015 08:33 AM
53 replies to this topic
#16
Posted 22 March 2015 - 10:20 AM
#17
Posted 22 March 2015 - 05:49 PM
Lots of pictures and description of how the floor fitting goes please, that's exactly what I plan to do to my pickup in a few months time so I'll be watching with interest!
#18
Posted 22 March 2015 - 06:32 PM
Will do, just waiting on another delivery from m-machine and i will be good to go
#19
Posted 22 March 2015 - 07:30 PM
Great - my floors a patchwork quilt of bodgery and oversills and I was looking at these floor assemblies in the m machine catalogue thinking they would be the way to go.
Did you have much trouble getting the old heel board out from under the end of the load bay ?
Did you have much trouble getting the old heel board out from under the end of the load bay ?
#20
Posted 22 March 2015 - 07:44 PM
It was fairly easy, the worst part was finding all the spot welds in the load bed but the spot weld drill bit i used was a god send.
The load bed is being replace but i have been as careful as possible so that i can use it for future projects.
The load bed is being replace but i have been as careful as possible so that i can use it for future projects.
#21
Posted 24 March 2015 - 03:48 PM
Looks like a good project, looking forward to seeing progress on this one.
#22
Posted 22 April 2015 - 09:50 PM
Another update on the van, got home on Wednesday so have stripped the remaining panels that require replacement -
Replaced rear arches, corners and lower valances
Fitted the floors and wheel wells which took a bit of time to get spot on but really happy with the quality of M-Machine work
Alot more to get on with, hoping to have toe board fitted and all major welding complete
Replaced rear arches, corners and lower valances
Fitted the floors and wheel wells which took a bit of time to get spot on but really happy with the quality of M-Machine work
Alot more to get on with, hoping to have toe board fitted and all major welding complete
#23
Posted 22 April 2015 - 09:53 PM
Wow, what a leap forward!
Really well done.
Ben
#24
Posted 22 April 2015 - 10:09 PM
Thanks Ben
#26
Posted 23 April 2015 - 05:54 PM
Great work there. How was the fit of the m machine floor assembly? Any problems?
#27
Posted 23 April 2015 - 07:33 PM
I would recommend the floor assembly and also load bed assembly to anyone, I did not need to do any modifications to either part and the workmanship they put into thier products is excellent.
#28
Posted 23 April 2015 - 07:38 PM
Awesome job!
#29
Posted 23 April 2015 - 09:43 PM
Wow just had a read through this, and you don't hang around with the work you have got loads done not long until it's a complete van.
0 user(s) are reading this topic