The planning permission we got is for a 2 story side extension where the drive goes past the house and a single story pitched roof extension across the back of the whole thing... this will give us a playroom, Walk in shower/Wet room and big Kitchen/dining/garden room downstairs and a big bedroom with ensuite upstairs (and the provision for a further bedroom and ensuite in the loft later on.
We got the price for the work from my brother on monday, paid him on tuesday, he came round with a builder on wednesday and they started today!!!
The old patio and pathways have all been demolished and skipped away and we have half of the footings dug, all the digging will be done by tommorow lunchtime and concrete should be poured at some point in the afternoon ready for the real building to start on monday.. by the end of next week, the ground floor layout should be complete ready for the fist floor joists which i will do at the weekend and it is entirely possible that the roof will be nearly done when we get home from riviera run!!!!! i'll do dome pics if anyones interested!!!!!
#2
Posted 13 April 2007 - 03:14 AM
#3
Posted 13 April 2007 - 07:30 AM
#4
Posted 13 April 2007 - 09:49 AM
#5
Posted 13 April 2007 - 11:55 AM
#6
Posted 13 April 2007 - 12:02 PM
Somethings not right on those plans... I don't see a double garage??
no??? you see to the left of the entrance hall... a room easily big enough for a mini... which had a pit in it on the first set of drawings and garage door on the front.... it now says "PLAYROOM".
#7
Posted 13 April 2007 - 01:23 PM
#8
Posted 13 April 2007 - 01:25 PM
#9
Posted 13 April 2007 - 01:53 PM
i tried telling them i have been there twice as my sewer pipe runs into her manhole, then back across my garden and i had to make sure it wasn't blocked, the second time was to clear some spoil which had fallen off the digger on to the drive..... The wall has been unsafe since we've been here and nearly went over when i took some tree roots out last year.. told neighbor i was doing it and that if it damaged the wall i would rebuild it and if the removal of the roots damaged her drive that i would re-lay her drive.... they are basically trying to say that i should have waited for her to come back before starting groundworks....
they are always staring out the window at us when i'm working on the car or on the house and the only things they have ever said dince the day we moved in were "you are going to sweep the road after doing that i hope"
Like it's their ***king road????
#10
Posted 13 April 2007 - 04:37 PM
Pics please.... but not of ur builders bum... or you on a 'tea break'!
#11
Posted 13 April 2007 - 05:08 PM
Mupets! It's kinda refreshing to see such a different project!
Pics please.... but not of ur builders bum... or you on a 'tea break'!
No power..... builders dug through the power cable at 3 oclock and i'm waiting for southern electric!!! i just found out that if i sit at the top of the stairs, i can piggyback other peoples wireless connections!!!! if i know who they were, i'd ask permission... if its the twot over the road i'm going to delete all his files!!!!!!!
#12
Posted 13 April 2007 - 05:30 PM
#13
Posted 13 April 2007 - 05:39 PM
#14
Posted 13 April 2007 - 09:09 PM
#15
Posted 13 April 2007 - 09:43 PM
0 user(s) are reading this topic
0 members, 0 guests, 0 anonymous users